From Radio Free Asia: Laos Minister: ‘Neighbors Not Against Xayaburi’.

Two months ago, Lao Foreign Minister Thongloun Sisoulith announced at an ASEAN ministerial meeting that the dam project has been put off pending further studies, earning praise from many delegates.

At the same time, the official media in Vientiane gave a different story, saying the government will continue to allow developer Ch. Karnchang, a Thai company, to proceed with “scheduled” activities at the construction site, including the resettlement of affected villagers.

Independent groups who visited the project site also confirmed that construction work is indeed continuing.

Following subsequent statements by Lao officials, it was assumed by many that Laos has allowed the developer to begin initial construction pending further studies on the sustainability of the project.

Comprehensive review

Daravong’s remarks this week that Cambodia and Vietnam were not opposed to the project contradict previous statements by the two countries, which have jointly urged Laos to suspend the dam.

Te Navuth, secretary general of Cambodia’s National Mekong Committee, said in July that the two countries have asked Laos to allow more time for a comprehensive review of the dam.

“Its aim is to require Laos to extend the consultation time for the dam and wait for the results of research that show the dam’s [potential] impact on the mainstream Mekong River,” he said.

In April, Lim Kean Hor, Cambodia’s water resources minister, also demanded in a letter to his Lao counterpart Noulinh Sinbandhit that construction on the dam be suspended pending an environmental impact assessment.

The Mekong River Commission (MRC), an intergovernmental body including Cambodia, Laos, Thailand, and Vietnam which manages development along Southeast Asia’s main waterway, had ruled that the dam project should not proceed until further assessment was conducted.

The decision followed an earlier recommendation by an expert study group for a 10-year moratorium on all mainstream Mekong dams due to a need for further research on their potentially catastrophic environmental and socioeconomic impact.

Minister Daravong denied that Cambodia and Vietnam are calling for a halt of the dam, saying that reports of their objections were simply not true.

The minister insists that the dam will be able to produce safe and clean energy and that it will not have any adverse environmental impact on neighboring countries.

Preparations for construction of the dam, including clearing the riverbank, have already begun, though the work is currently on hold due to the start of the rainy season, he said. 

Thailand

Environmental groups in Thailand, Cambodia, and Vietnam have staged protests against the Xayaburi dam, saying it is likely to damage the Mekong ecosystem and fisheries and the food security of the people downstream.

Last month, a group of Thai villagers opposed to the dam submitted a lawsuit against five Thai government agencies, saying the government should not have agreed to purchase electricity from the dam without further study. 

The project is being financed by a consortium of Thai banks. 

Laos, which hopes to become the “battery” of Southeast Asia by selling hydroelectric power to its neighbors, has over 70 dams planned on its rivers.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s